CHATHAM – Chatham’s sewer construction contractor plans continue this week, with two crews working simultaneously.
Both have been working at multiple locations since the beginning of the month and are focused this week Independence Lane, The Cornfield, and Inlet Road before moving onto the Wineberry.
Motorists will be helped navigating the sites by signage and police.
Affected roads will be open nights and weekends. The work is scheduled for Monday through Friday 7:00am to 5:00pm, but may be extended to 7:00pm as needed.
The town has set up a web site with updated information at chathamscproject.info.