CHATHAM – Roadway restoration and paving work related to Chatham’s sewer construction project has resumed for the fall.
Crews will continue cleanup, keyways cutting and castings adjustment work today before beginning the top course of paving tomorrow on Absegami Run/Oyster Bluff.
Paving work will continue through Friday on Oyster Pond Furlong, Oyster Pond Lane, Jane’s Way, Earle’s Way, The Cornfield, Wheldon Way and Shattuck Place.
The paving of Inlet Road and Spinnaker Lane is scheduled to begin next Tuesday, but could begin this week if all other roads are completed early.
Work hours are weekdays from 7 a.m. to 5 p.m.
Roads will be passable at the end of each day. Police details and contractors will work with residents to ensure their needs for access are met. Police and signs will also assist motorists with detours.
Lawn restoration and other work will be completed following the top course of paving.
Updated schedule information can be found by visiting www.chathamscproject.info.