HYANNIS – The Town of Barnstable has announced a delay in its Great Streets Downtown Hyannis project, pushing the planned conversion of downtown streets to two-way traffic and construction of a new roundabout at the busy Six Points intersection into fall 2027 and potentially 2028.
The revised timeline, announced Wednesday, November 18, represents a change from earlier projections that major portions of the project could be completed by summer 2027.
According to the Barnstable Department of Public Works, the delay is primarily due to ongoing coordination with utility companies and the project’s contractor over the relocation of underground utilities.
Those relocations must be completed before construction of the new roundabout can move forward.
Town officials said the decision to adjust the schedule now is intended to minimize disruptions to downtown Hyannis businesses, residents and visitors during the busy summer tourism season.
Despite the delay, officials emphasized that the overall design and planned improvements remain unchanged.
The Great Streets project is a major redesign of downtown Hyannis intended to improve traffic circulation, pedestrian safety and accessibility. A central component involves converting portions of the existing one-way street network, including Main Street, South Street, Ocean Street and Old Colony Road, to two-way travel.
The project also includes replacing the complicated Six Points intersection with a modern roundabout designed to improve traffic flow and simplify vehicle movements through the area.
Construction will continue on other portions of the project, including accessible curb ramps along Main Street, sidewalk improvements on North Street and additional utility, drainage and curb work throughout the project area.
All existing traffic signals and pedestrian crossing signals will remain operational during construction and throughout the summer season.
As summer approaches, the town expects to install temporary pedestrian connections and restore disturbed areas with loam, seed or gravel where appropriate.
Barnstable officials reiterated their commitment to avoiding active roadway construction during the peak summer tourism season.
Crews have been working at Six Points on drainage improvements, excavation and underground conduits since October. The work has also included preparations for utility relocations and pedestrian improvements along Main Street.
In the town’s most recent construction update for November 16-20, officials reported that Eversource was expected to begin installing utility poles in the project area. Construction was scheduled weekdays from 7 a.m. to 3 p.m., with intermittent lane closures but no full road closures anticipated.
The Great Streets initiative has been in development since 2022. In addition to the traffic changes, plans include bicycle accommodations, shared-use paths, improved crosswalks and additional on-street parking. The town has said existing Main Street parking will be retained.
The Department of Public Works will now work with its contractor to establish a revised construction schedule and announce updated milestones as they become available.
Weekly construction updates will continue, along with coordination with downtown businesses and other stakeholders.
Additional information is available at Barnstable.gov/GreatStreetsHyannis.
Residents and business owners with construction-related questions can contact Barnstable DPW at 508-790-6400.