Work On Schedule for Falmouth Water, Sewer Projects

CCB MEDIA PHOTO Crews work off Gifford Street on the project to install at water filtration plant.

CCB MEDIA PHOTO
Crews work off Gifford Street on the project to install at water filtration plant.

FALMOUTH – Construction of the new water filtration plant is underway in Falmouth.

Crews have excavated about 46,000 cubic yards in the 13-acre site off Gifford Street and have installed an electrical duct bank and a water main. Falmouth Department of Public Works Director Raymond Jack updated selectmen on the progress of the project at a meeting last month.

The $49 million project has a completion date of summer 2017 and is currently on schedule, Jack said. Work began in late April.

Work is also underway on the large-scale sewer project connecting more than 1,400 homes to the new plant. Three crews are installing the lines.